Question : 91. The following data relate to direct labor costs for February: Actual : 1233877

 

91. The following data relate to direct labor costs for February: 

Actual costs

7,700 hours at $13

Standard costs

7,000 hours at $9

 

 

What is the direct labor time variance? A. $9,100 favorableB. $9,100 unfavorableC. $6,300 unfavorableD. $6,300 favorable

92. The following data relate to direct labor costs for February: 

Actual costs

7,700 hours at $13

Standard costs

7,000 hours at $9

 

 

What is the direct labor rate variance? A. $28,000 favorableB. $28,000 unfavorableC. $30,800 favorableD. $30,800 unfavorable

93. The following data is given for the Walker Company: 

Budgeted production

1,000 units

Actual production

   980 units

Materials:

 

  Standard price per lb

$2.00

  Standard pounds per completed unit

12

  Actual pounds purchased and used in production

11,800

  Actual price paid for materials

$23,000

Labor:

 

  Standard hourly labor rate

$14 per hour

  Standard hours allowed per completed unit

4.5

  Actual labor hours worked

4,560

  Actual total labor costs

$62,928

Overhead:

 

  Actual and budgeted fixed overhead

$27,000

  Standard variable overhead rate

$3.50 per standard labor hour

  Actual variable overhead costs

$15,500

 

 

  Overhead is applied on standard labor hours. The direct labor rate variance is: A. 912UB. 912FC. 2,100UD. 2,100F

94. The following data is given for the Walker Company: 

Budgeted production

1,000 units

Actual production

   980 units

Materials:

 

  Standard price per lb

$2.00

  Standard pounds per completed unit

12

  Actual pounds purchased and used in production

11,800

  Actual price paid for materials

$23,000

Labor:

 

  Standard hourly labor rate

$14 per hour

  Standard hours allowed per completed unit

4.5

  Actual labor hours worked

4,560

  Actual total labor costs

$62,928

Overhead:

 

  Actual and budgeted fixed overhead

$27,000

  Standard variable overhead rate

$3.50 per standard labor hour

  Actual variable overhead costs

$15,500

 

 

  Overhead is applied on standard labor hours. The direct labor time variance is: A. 912FB. 912UC. 2,100UD. 2,100F

95. The following data is given for the Walker Company: 

Budgeted production

26,000 units

Actual production

27,500 units

Materials:

 

  Standard price per ounce

$6.50

  Standard ounces per completed unit

8

  Actual ounces purchased and used in production

228,000

  Actual price paid for materials

$1,504,800

Labor:

 

  Standard hourly labor rate

$22 per hour

  Standard hours allowed per completed unit

6.6

  Actual labor hours worked

183,000

  Actual total labor costs

$4,020,000

Overhead:

 

  Actual and budgeted fixed overhead

$1,029,600

  Standard variable overhead rate

$24.50 per standard labor hour

  Actual variable overhead costs

$4,520,000

 

 

  Overhead is applied on standard labor hours. The direct labor rate variance is: A. 6,000UB. 6,000FC. 33,000FD. 33,000U

96. The following data is given for the Walker Company: 

Budgeted production

26,000 units

Actual production

27,500 units

Materials:

 

  Standard price per ounce

$6.50

  Standard ounces per completed unit

8

  Actual ounces purchased and used in production

228,000

  Actual price paid for materials

$1,504,800

Labor:

 

  Standard hourly labor rate

$22 per hour

  Standard hours allowed per completed unit

6.6

  Actual labor hours worked

183,000

  Actual total labor costs

$4,020,000

Overhead:

 

  Actual and budgeted fixed overhead

$1,029,600

  Standard variable overhead rate

$24.50 per standard labor hour

  Actual variable overhead costs

$4,520,000

 

 

  Overhead is applied on standard labor hours. The direct labor time variance is: A. 6,000FB. 6,000UC. 33,000UD. 33,000F

97. The Joyner Corporation had 8,000 actual direct labor hours at an actual rate of $12.20 per hour. Original production had been budgeted for 1,100 units, but only 1,000 units were actually produced. Labor standards were 7.5 hours per completed unit at a standard rate of $13 per hour. Compute the labor rate variance. A. 6,400UB. 6,400FC. 6,500UD. 6,500U

98. The Joyner Corporation had 8,000 actual direct labor hours at an actual rate of $12.20 per hour. Original production had been budgeted for 1,100 units, but only 1,000 units were actually produced. Labor standards were 7.5 hours per completed unit at a standard rate of $13 per hour. Compute the labor time variance. A. 6,400FB. 6,400UC. 6,500UD. 6,500F

99. 

 

Standard

Actual

Material Cost Per Yard

$2.00

$2.04

Standard Yards per Unit

5 yards

4.75 yards

Units of Production

 

9,450

 

 

 

Calculate the Total Direct Materials cost variance using the above information: A. $2,929.50 UnfavorableB. $2,929.50 FavorableC. $3,780.00 UnfavorableD. $3,562.50 Favorable

100. 

 

Standard

Actual

Material Cost Per Yard

$2.00

$2.04

Standard Yards per Unit

5 yards

4.75 yards

Units of Production

 

9,450

 

 

 

Calculate the Total Direct Materials Price variance using the above information: A. $1,795.50 FavorableB. $378 FavorableC. $1,795.50 UnfavorableD. $378 Unfavorable

 

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more