91. The following data relate to direct labor costs for February:
Actual costs
7,700 hours at $13
Standard costs
7,000 hours at $9
What is the direct labor time variance? A. $9,100 favorableB. $9,100 unfavorableC. $6,300 unfavorableD. $6,300 favorable
92. The following data relate to direct labor costs for February:
Actual costs
7,700 hours at $13
Standard costs
7,000 hours at $9
What is the direct labor rate variance? A. $28,000 favorableB. $28,000 unfavorableC. $30,800 favorableD. $30,800 unfavorable
93. The following data is given for the Walker Company:
Budgeted production
1,000 units
Actual production
980 units
Materials:
Standard price per lb
$2.00
Standard pounds per completed unit
12
Actual pounds purchased and used in production
11,800
Actual price paid for materials
$23,000
Labor:
Standard hourly labor rate
$14 per hour
Standard hours allowed per completed unit
4.5
Actual labor hours worked
4,560
Actual total labor costs
$62,928
Overhead:
Actual and budgeted fixed overhead
$27,000
Standard variable overhead rate
$3.50 per standard labor hour
Actual variable overhead costs
$15,500
Overhead is applied on standard labor hours. The direct labor rate variance is: A. 912UB. 912FC. 2,100UD. 2,100F
94. The following data is given for the Walker Company:
Budgeted production
1,000 units
Actual production
980 units
Materials:
Standard price per lb
$2.00
Standard pounds per completed unit
12
Actual pounds purchased and used in production
11,800
Actual price paid for materials
$23,000
Labor:
Standard hourly labor rate
$14 per hour
Standard hours allowed per completed unit
4.5
Actual labor hours worked
4,560
Actual total labor costs
$62,928
Overhead:
Actual and budgeted fixed overhead
$27,000
Standard variable overhead rate
$3.50 per standard labor hour
Actual variable overhead costs
$15,500
Overhead is applied on standard labor hours. The direct labor time variance is: A. 912FB. 912UC. 2,100UD. 2,100F
95. The following data is given for the Walker Company:
Budgeted production
26,000 units
Actual production
27,500 units
Materials:
Standard price per ounce
$6.50
Standard ounces per completed unit
8
Actual ounces purchased and used in production
228,000
Actual price paid for materials
$1,504,800
Labor:
Standard hourly labor rate
$22 per hour
Standard hours allowed per completed unit
6.6
Actual labor hours worked
183,000
Actual total labor costs
$4,020,000
Overhead:
Actual and budgeted fixed overhead
$1,029,600
Standard variable overhead rate
$24.50 per standard labor hour
Actual variable overhead costs
$4,520,000
Overhead is applied on standard labor hours. The direct labor rate variance is: A. 6,000UB. 6,000FC. 33,000FD. 33,000U
96. The following data is given for the Walker Company:
Budgeted production
26,000 units
Actual production
27,500 units
Materials:
Standard price per ounce
$6.50
Standard ounces per completed unit
8
Actual ounces purchased and used in production
228,000
Actual price paid for materials
$1,504,800
Labor:
Standard hourly labor rate
$22 per hour
Standard hours allowed per completed unit
6.6
Actual labor hours worked
183,000
Actual total labor costs
$4,020,000
Overhead:
Actual and budgeted fixed overhead
$1,029,600
Standard variable overhead rate
$24.50 per standard labor hour
Actual variable overhead costs
$4,520,000
Overhead is applied on standard labor hours. The direct labor time variance is: A. 6,000FB. 6,000UC. 33,000UD. 33,000F
97. The Joyner Corporation had 8,000 actual direct labor hours at an actual rate of $12.20 per hour. Original production had been budgeted for 1,100 units, but only 1,000 units were actually produced. Labor standards were 7.5 hours per completed unit at a standard rate of $13 per hour. Compute the labor rate variance. A. 6,400UB. 6,400FC. 6,500UD. 6,500U
98. The Joyner Corporation had 8,000 actual direct labor hours at an actual rate of $12.20 per hour. Original production had been budgeted for 1,100 units, but only 1,000 units were actually produced. Labor standards were 7.5 hours per completed unit at a standard rate of $13 per hour. Compute the labor time variance. A. 6,400FB. 6,400UC. 6,500UD. 6,500F
99.
Standard
Actual
Material Cost Per Yard
$2.00
$2.04
Standard Yards per Unit
5 yards
4.75 yards
Units of Production
9,450
Calculate the Total Direct Materials cost variance using the above information: A. $2,929.50 UnfavorableB. $2,929.50 FavorableC. $3,780.00 UnfavorableD. $3,562.50 Favorable
100.
Standard
Actual
Material Cost Per Yard
$2.00
$2.04
Standard Yards per Unit
5 yards
4.75 yards
Units of Production
9,450
Calculate the Total Direct Materials Price variance using the above information: A. $1,795.50 FavorableB. $378 FavorableC. $1,795.50 UnfavorableD. $378 Unfavorable
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more