51. Speedy CouriersSpeedy Couriers documented the miles driven and total vehicle costs for the past five months as follows:
Number of miles
Total vehicle costs
January
1,600
$3,600
February
2,000
4,600
March
1,500
3,450
April
1,800
3,900
May
2,200
4,500
Refer to the Speedy Couriers information above. Using the high/low method, what is the cost equation to predict total vehicle costs? A. Y = $985 + $1.64xB. Y = $4,500 + $2.05xC. Y = $560 + $2.30xD. Y = $1,200 + $1.50x
52. Speedy CouriersSpeedy Couriers documented the miles driven and total vehicle costs for the past five months as follows:
Number of miles
Total vehicle costs
January
1,600
$3,600
February
2,000
4,600
March
1,500
3,450
April
1,800
3,900
May
2,200
4,500
Refer to the Speedy Couriers information above. Using the high/low method, if Speedy expects to drive 1,750 miles in June, what will be expected total vehicle costs? A. $3,825.00B. $4,585.00C. $8,087.50D. $3,855.00
53. Denver ManufacturingDenver Manufacturing would like to do a better job budgeting for maintenance costs and, consequently, they have prepared a schedule showing maintenance costs and units produced for the past five months as follows:
Number ofunits produced
Totalmaintenance costs
January
5,400
$4,800
February
6,600
5,180
March
4,900
4,500
April
5,600
4,900
May
6,000
5,490
Refer to the Denver Manufacturing information above. Using the high/low method, what is the cost equation to predict total maintenance costs? A. Y = $90 + $.90xB. Y = $2,540 + $.40xC. Y = $1,646 + $.5824xD. Y = $2.50x – $11,320
54. Denver ManufacturingDenver Manufacturing would like to do a better job budgeting for maintenance costs and, consequently, they have prepared a schedule showing maintenance costs and units produced for the past five months as follows:
Number ofunits produced
Totalmaintenance costs
January
5,400
$4,800
February
6,600
5,180
March
4,900
4,500
April
5,600
4,900
May
6,000
5,490
Refer to the Denver Manufacturing information above. Using the high/low method, if Denver expects to produce 5,000 units in June, what will be budgeted total maintenance costs? A. $4,590B. $4,558C. $4,540D. $4,363
55. When comparing a “pre-tax cost” and an “after-tax cost”, which of the following is true? A. The after-tax cost will be greater than the pretax cost.B. They will be the same amount.C. The pre-tax cost will be greater than the after-tax cost.D. The higher the tax rate, the lower the difference in the amount between them.
56. The after-tax benefit of a taxable cash receipt can be calculated as follows: A. After-tax benefit = Pretax receipt ´ tax rateB. After-tax benefit = Pretax receipt ´ (1 – tax rate)C. After-tax benefit = Pretax receipt ´ (1 + tax rate)D. After-tax benefit = Pretax receipt ¸ tax rate
57. After-tax income can be calculated as follows: A. After-tax income = Pretax income ´ tax rateB. After-tax income = Pretax income ¸ (1 – tax rate)C. After-tax income = Pretax income ´ (1 + tax rate)D. After-tax income = Pretax income ´ (1 – tax rate)
58. The manager of a company is considering a special project that will increase sales revenue by $27,500 without affecting costs. If the company has a tax rate of 40%, what will be the after-tax income? A. $16,500B. $11,000C. $27,500D. $38,500
59. Blossom Products is considering a special project that will increase sales revenue by $127,000 without affecting costs. If the company has a tax rate of 40%, what will be the after-tax income? A. $ 50,800B. $ 76,200C. $127,000D. $203,200
60. Putnam Distributors is contemplating whether or not to accept a special order. Putnam wishes to have after-tax cash receipts of $54,000 if they accept the order. If Putnam has a tax rate of 40%, what is the price the customer should be charged for their order? A. $32,400B. $21,600C. $90,000D. $54,000
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more