Question : 122.Barnes Company produces men’s ties. The following budgeted amounts were : 1302881

 

 

122.Barnes Company produces men’s ties. The following budgeted amounts were provided by management for the current year:

 

CategoryStandard InputsStandard Cost

Direct materials1.1 yards per tie$4.00 per yard

Direct labor0.32 hours per tie$9.00 per hour

 

Barnes produced and sold 4,000 ties during 2014. Actual performance for the year is:

Direct MaterialsDirect Labor

Yards used in production4,100Labor hours incurred1,240

Yards purchased3,900Actual cost per hour$9.25

Actual cost per yard$3.75

 

How much is the labor rate variance?

A.$310 unfavorable

B.$360 favorable

C.$50 favorable

D.$1,000 unfavorable

 

123.Barnes Company produces men’s ties. The following budgeted amounts were provided by management for the current year:

 

CategoryStandard InputsStandard Cost

Direct materials1.1 yards per tie$4.00 per yard

Direct labor0.32 hours per tie$9.00 per hour

 

Barnes produced and sold 4,000 ties during 2014. Actual performance for the year is:

Direct MaterialsDirect Labor

Yards used in production4,100Labor hours incurred1,240

Yards purchased3,900Actual cost per hour$9.25

Actual cost per yard$3.75

 

How much is the labor efficiency variance?

A.$310 unfavorable

B.$360 favorable

C.$50 favorable

D.$1,000 unfavorable

 

124.Capital Leather Company produces leather footballs. The standard cost for each football is:

 

Direct material2 feet of leather at $4.00 per foot

Direct labor1.5 hours at $12.00 per hour

 

During February, 1,200 footballs were produced and 2,600 feet of leather were purchased at $4.25 per foot. Production usage was 2,300 feet. Direct labor cost incurred was $20,930 for 1,820 hours. How much is the direct material price variance?

A.$650 favorable

B.$650 unfavorable

C.$575 favorable

D.$575 unfavorable

 

125.Capital Leather Company produces leather footballs. The standard cost for each football is:

 

Direct material2 feet of leather at $4.00 per foot

Direct labor1.5 hours at $12.00 per hour

 

During February, 1,200 footballs were produced and 2,600 feet of leather were purchased at $4.25 per foot. Production usage was 2,300 feet. Direct labor cost incurred was $20,930 for 1,820 hours. How much is the direct material quantity variance?

A.$100 unfavorable

B.$400 favorable

C.$800 favorable

D.$800 unfavorable

 

126.Capital Leather Company produces leather footballs. The standard cost for each football is:

 

Direct material2 feet of leather at $4.00 per foot

Direct labor1.5 hours at $12.00 per hour

 

During February, 1,200 footballs were produced and 2,600 feet of leather were purchased at $4.25 per foot. Production usage was 2,300 feet. Direct labor cost incurred was $20,930 for 1,820 hours. How much is the direct labor rate variance?

A.$900 favorable

B.$900 unfavorable

C.$910 favorable

D.$910 unfavorable

 

127.Capital Leather Company produces leather footballs. The standard cost for each football is:

 

Direct material2 feet of leather at $4.00 per foot

Direct labor1.5 hours at $12.00 per hour

 

During February, 1,200 footballs were produced and 2,600 feet of leather were purchased at $4.25 per foot. Production usage was 2,300 feet. Direct labor cost incurred was $20,930 for 1,820 hours. How much is the direct labor efficiency variance?

A.$20 unfavorable

B.$240 unfavorable

C.$360 unfavorable

D.$360 favorable

 

128.Standard Gears produces lawn mower gears. It uses units as the cost driver for overhead. The following information was provided concerning its standard cost system:

 

Actual DataBudgeted and Standard Data

Produced12,400 unitsBudgeted units12,500 units

Materials purchased4,650 lbs. for a total cost of $32,550Budgeted materials0.40 lb. @ $7.10 per lb.

Materials used4,700 lbs.Budgeted labor36 minutes @ $11.00 per hour

Labor worked7,460 hrs. costing $79,822Budgeted variable overhead$35,625

Actual overheadFixed: $84,800

Variable $36,100Budgeted fixed overhead$85,500

 

How much is the standard cost of each lawn mower gear?

A.$25.59

B.$19.13

C.$9.44

D.$19.28

 

129.Standard Gears produces lawn mower gears. It uses units as the cost driver for overhead. The following information was provided concerning its standard cost system:

 

Actual DataBudgeted and Standard Data

Produced12,400 unitsBudgeted units12,500 units

Materials purchased4,650 lbs. for a total cost of $32,550Budgeted materials0.40 lb. @ $7.10 per lb.

Materials used4,700 lbs.Budgeted labor36 minutes @ $11.00 per hour

Labor worked7,460 hrs. costing $79,822Budgeted variable overhead$35,625

Actual overheadFixed: $84,800

Variable $36,100Budgeted fixed overhead$85,500

 

How much is the direct material price variance?

A.$465 favorable

B.$1,846 favorable

C.$470 favorable

D.$2,201 favorable

 

130.Standard Gears produces lawn mower gears. It uses units as the cost driver for overhead. The following information was provided concerning its standard cost system:

 

Actual DataBudgeted and Standard Data

Produced12,400 unitsBudgeted units12,500 units

Materials purchased4,650 lbs.; total cost $32,550Budgeted materials0.40 lb. @ $7.10 per lb.

Materials used4,700 lbs.Budgeted labor36 minutes @ $11.00/hour

Labor worked7,460 hrs. costing $79,822Budgeted variable overhead$35,625

Actual overheadFixed: $84,800

Variable $36,100Budgeted fixed overhead$85,500

 

What is the direct material quantity variance?

A.$465 favorable

B.$1,846 favorable

C.$470 favorable

D.$2,201 favorable

 

131.Billy Bob Subs has the following standard cost to produce a king size party sub sandwich.

 

Direct materials = 4 pounds @ $3.00 per pound = $12.00 per sub

Direct labor = 1/2 hour @ $8.00 per hour = $4.00 per sub

 

During December, the company produced 1,000 party subs, bought 4,300 pounds and used 4,100 pounds of meat at $3.20 per pound, and used 490 hours of labor at a total cost of $4,018. How much is the direct labor rate variance?

A.$98 unfavorable

B.$18 unfavorable

C.$80 favorable

D.$178 unfavorable

 

 

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more