Question and assingment are posted here read the assignment and the

 

Greendale Stadium Case

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the 2014 season. A penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes.

ASSIGNMENT

Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions:

  1. Will the project be able to be completed by the May 20 deadline? How long will it take?
  2. What is the critical path for the project?
  3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.

CASE APPENDIX: TECHNICAL DETAILS OF THE GREENDALE BASEBALL STADIUM

The baseball stadium is an outdoor structure with a retractable roof. The project begins with clearing the site, an activity that lasts 70 days. Once the site is clear, work can start simultaneously on the structure itself and demolishing an adjacent building site. This demolition is necessary to create a construction stage for storing materials and equipment. It will take 30 days to demolish the buildings and another 70 days to set up the construction site.

Page 203 

TABLE 6.3 Greendale Stadium Case

image

The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl can occur (120 days).

Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days).

The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed. At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made operational (90 days). Once all activities are completed it will take 20 days to inspect the stadium.

For purposes of this case assume the following:

  1. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
  2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.
  3. The construction crew work Monday through Friday.

assignment is this one:

 

Greendale Project ReDux
Due Week 8 and worth 90 points

This assignment consists of two (2) parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for.

Part A: Project Schedule
(Submit as one [1] Microsoft Project file)

  1. Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the “Greendale Stadium Case” located at the end of Chapter 6, and incorporating the following constraints.
    Note: When you create your MS Project schedule, you will need to update your project per the following constraints: 
    • The project must consist of at least twenty (20) tasks.
    • Each task must have a start and finish date that matches the duration noted in the assignment. 
    • Each task must be assigned to a resource (e.g., Demolishing Crew; Construction Crew; Landscaping Crew). 
    • Assume that the crew works during normal weekdays (no weekend work) under normal conditions (8 hours per day).  
    • In terms of holidays, you can assume no work will be done the following days: New Year’s Day, President’s Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year’s Eve.

Part B: Written Response
(Submit as a Microsoft Word file)

  1. Respond to the following questions in a one to two (1-2) page paper based on your project schedule. 
    • When will the project be completed? 
    • What is the critical path for the project?
    • How much slack / float is in your project? What activities have the greatest slack / float?
    • Identify the top three (3) activities that you believe could impact the project completion date.
    • What additional activities you would add to this project to make it more complete, from a project management viewpoint?  
  2. Format your assignment according to the following formatting requirements:
    • Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.
    • Include a cover page containing the title of the assignment, the student’s name, the professor’s name, the course title, and the date. The cover page is not included in the required page length.
Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more