Project management ch 13 – progress and performance measurement and

Progress and Performance Measurement and Evaluation
Project Management Ch 13
6th Edition

 

 

1    
The second step in the project control process for measuring and evaluating project performance is to
    A)
Review the baseline plan with top management
    B)
Analyze inputs to control system
    C)
Compare plan against actual
    D)
Measure progress and performance
    E)
Review spending with team members
    

 
2    
A ___________ Gantt chart is a simple and effective way to depict progress on a project.
    A)
Baseline
    B)
Control
    C)
Variance
    D)
Tracking
    E)
Simple
    

 
3    
A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a
    A)
Project control chart
    B)
Gantt chart
    C)
PERT chart
    D)
Network diagram
    E)
Milestone chart
    

 
4    
The earned value system starts with the time-phased costs that provide the project baseline, which is called the
    A)
Planned budgeted value of work scheduled
    B)
Planned budgeted value of work completed
    C)
Earned value of work scheduled
    D)
Scheduled value of work scheduled
    E)
Scheduled value of work completed
    

 
5    
The cost variance for a project is calculated by
    A)
EV-AC
    B)
AC-SV
    C)
PV-EV
    D)
CV-EV
    E)
EV-PV
    

 
6    
Baseline project budgets are derived from
    A)
The organization’s overall budget
    B)
Time-phasing the work packages
    C)
Top management directions
    D)
The total direct, direct project overhead and G&A overhead costs
    E)
The earned value system
    

 
7    
Of the following costs, which are NOT included in baseline?
    A)
Suppliers
    B)
Equipment
    C)
Labor
    D)
Budget reserves
    E)
Contractors
    

 
8    
Which of the following methods will measure the cost efficiency of the work accomplished to date?
    A)
SV/CV
    B)
EV/PV
    C)
EV/AC
    D)
AC/SV
    E)
AC/CV
    

 
9    
A CPI or SPI value less than one indicates that the project is
    A)
Under cost or behind schedule
    B)
Over cost or ahead of schedule
    C)
Under cost or ahead of schedule
    D)
Over cost or behind schedule
    E)
On cost or on schedule
    

 
10    
The value that tells you the planned value of work that has actually been completed is the
    A)
SV
    B)
PV
    C)
EV
    D)
AC
    E)
CV
    

 
11    
The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the
    A)
PCIC
    B)
VAC
    C)
CPI
    D)
SPI
    E)
TCPI
    

 
12    
Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the
    A)
SV
    B)
TCPI
    C)
CPI
    D)
SPI
    E)
PCIB
    

 
13    
Sally receives the following information on her project: PV=100, AC=75, EV=100. How well is the project doing in terms of budget?
    A)
Right on budget
    B)
25 under budget
    C)
25 over budget
    D)
50 under budget
    E)
50 over budget
    

 
14    
Jessica just received the following information on her project: PV =200, EV=300, AC=250, BAC=1500, EAC=1208. In terms of cost at completion
    A)
The project will currently finish under budget
    B)
The project will currently finish over budget
    C)
The project will currently finish on budget
    D)
The project will currently finish behind schedule
    E)
There is insufficient information to draw conclusions
    

 
15    
Which of the following is NOT true regarding scope creep?
    A)
It commonly occurs late in projects
    B)
It is frequently unnoticed until time delays or cost overruns are observed
    C)
It wears down team motivation and cohesiveness
    D)
Project suppliers resent frequent changes
    E)
Scope changes can represent significant opportunity

 

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more