Question : 116.Pilot Protectors manufactures pocket knives in three processes and uses : 1302715

 

 

116.Pilot Protectors manufactures pocket knives in three processes and uses process costing. All materials are added at the start of the Forming Department process. The following unit information is available for March production for the Forming Department:

Beginning Work in Process (20% complete)              2,000

Plus: Units started              34,000

Units to account for              36,000

Less: Ending Work in Process (70% complete)                4,000

Units completed              32,000

 

The following costs are available for March for the Forming Department:

MaterialConversion CostTotal Cost

Beginning Work in Process              $ 11,800              $ 22,500              $   34,300

Current cost                65,600                64,500                 130,100

Total cost              $77,400              $87,000              $164,400

What is the total amount to be debited to the Forming Department’s Work in Process inventory account during March?

A.$130,100

B.$164,400

C.$13,228

D.$15,600

 

117.Pilot Protectors manufactures pocket knives in three processes and uses process costing. All materials are added at the start of the Forming Department process. The following information is available for March production for the Forming Department:

Beginning Work in Process (20% complete)    2,000

Plus: Units started              34,000

Units to account for              36,000

Less: Ending Work in Process (70% complete)                4,000

Units completed              32,000

 

The following costs are available for March:

MaterialConversion CostTotal Cost

Beginning Work in Process              $ 11,800              $  22,500              $   34,300

Current cost              65,600                64,500                 130,100

Total cost              $77,400              $87,000              $164,400

What are the equivalent units for conversion costs in the Forming Department?

A.32,000 units

B.36,000 units

C.34,800 units

D.2,800 units

 

118.Pilot Protectors manufactures pocket knives in three processes and uses process costing. All materials are added at the start of the Forming Department process. The following information is available for March production for the Forming Department:

Beginning Work in Process (20% complete)    2,000

Plus: Units started              34,000

Units to account for              36,000

Less: Ending Work in Process (70% complete)                4,000

Units completed              32,000

 

The following costs are available for March:

MaterialConversion CostTotal Cost

Beginning Work in Process              $ 11,800              $  22,500              $   34,300

Current cost              65,600                64,500                 130,100

Total cost              $77,400              $87,000              $164,400

What is the cost per equivalent unit for materials?

A.$2.15

B.$2.50

C.$2.22

D.$4.72

 

119.Pilot Protectors manufactures pocket knives in three processes and uses process costing. All materials are added at the start of the Forming Department process. The following information is available for March production for the Forming Department:

Beginning Work in Process (20% complete)    2,000

Plus: Units started              34,000

Units to account for              36,000

Less: Ending Work in Process (70% complete)                4,000

Units completed              32,000

 

The following costs are available for March:

MaterialConversion CostTotal Cost

Beginning Work in Process              $ 11,800              $  22,500              $   34,300

Current cost              65,600                64,500                 130,100

Total cost              $77,400              $87,000              $164,400

What is the cost of goods transferred to the next processing department during March?

A.$15,600

B.$148,800

C.$167,400

D.$130,100

120.Keystone Snow Boards Manufacturing Company produces entry-level snowboards and uses process costing. All materials are added at the start of the process. The following information on units is available for September production for the company’s Cutting Department:

Beginning Work in Process, 30% complete for conversion costs              14,000

Units started              125,000

Ending Work in Process, 60% complete for conversion costs              15,000

Units completed              124,000

 

The following costs are available for September:

MaterialConversion CostTotal Cost

Beginning Work in Process              $  8,200              $  1,350              $    9,550

Current cost                70,600                47,120                117,720

Total cost              $78,800              $48,470              $127,270

What is the dollar amount of the total costs to account for September in the Cutting Department?

A.$127,270

B.$117,720

C.$48,470

D.$78,800

 

121.Keystone Snow Boards Manufacturing Company produces entry-level snowboards and uses process costing. All materials are added at the start of the process. The following information on units is available for September production for the company’s Cutting Department:

Beginning Work in Process, 30% complete for conversion costs              14,000

Units started              125,000

Ending Work in Process, 60% complete for conversion costs              15,000

Units completed              124,000

 

The following costs are available for September:

MaterialConversion CostTotal Cost

Beginning Work in Process              $  8,200              $  1,350              $    9,550

Current cost                70,600                47,120              117,720

Total cost              $78,800              $48,470              $127,270

What are the equivalent units for conversion costs in September?

A.139,000 units

B.124,000 units

C.133,000 units

D.140,000 units

 

 

122.Keystone Snow Boards Manufacturing Company produces entry-level snowboards and uses process costing. All materials are added at the start of the process. The following information on units is available for September production for the company’s Cutting Department:

Beginning Work in Process, 30% complete for conversion costs              14,000

Units started              125,000

Ending Work in Process, 60% complete for conversion costs              15,000

Units completed              124,000

 

The following costs are available for September:

MaterialConversion CostTotal Cost

Beginning Work in Process              $  8,200              $  1,350              $    9,550

Current cost                70,600                47,120                117,720

Total cost              $78,800              $48,470              $127,270

Assume equivalent units for materials are 157,600 units. How much is the cost per unit for materials?

A.$0.50

B.$0.81

C.$0.57

D.$2.00

 

123.Rooftop Gutters produces polyurethane gutters and uses process costing. All materials are added at the start of the Forming Department process. The following information is available for units produced in the Forming Department for the month of April:

Beginning Work in Process, in linear feet

(20% complete with respect to conversion costs)              11,500

Units started              42,000

Ending Work in Process, in linear feet

(60% complete with respect to conversion costs)              9,000

Units completed              44,500

 

The following costs are available for April:

MaterialConversion CostTotal Cost

Beginning Work in Process              $11,600              $  8,540              $   20,140

Current cost                63,300                21,400                 84,700

Total cost              $74,900              $29,940              $104,840

What is the sum of total costs to account for?

A.$74,900

B.$104,840

C.$29,940

D.$144,760

124.Rooftop Gutters produces polyurethane gutters and uses process costing. All materials are added at the start of the Forming Department process. The following information is available for units produced in the Forming Department for the month of April:

Beginning Work in Process, in linear feet

(20% complete with respect to conversion costs)              11,500

Units started              42,000

Ending Work in Process, in linear feet

(60% complete with respect to conversion costs)              9,000

Units completed              44,500

 

The following costs are available for April:

MaterialConversion CostTotal Cost

Beginning Work in Process              $11,600              $  8,540              $   20,140

Current cost                63,300                21,400                 84,700

Total cost              $74,900              $29,940              $104,840

What are the equivalent units for conversion costs?

A.53,500 units

B.5,400 units

C.9,000 units

D.49,900 units

 

125.Rooftop Gutters produces polyurethane gutters and uses process costing. All materials are added at the start of the Forming Department process. The following information is available for units produced in the Forming Department for the month of April:

Beginning Work in Process, in linear feet

(20% complete with respect to conversion costs)              11,500

Units started              42,000

Ending Work in Process, in linear feet

(60% complete with respect to conversion costs)              9,000

Units completed              44,500

 

The following costs are available for April:

MaterialConversion CostTotal Cost

Beginning Work in Process              $11,600              $  8,540              $   20,140

Current cost                63,300                21,400                 84,700

Total cost              $74,900              $29,940              $104,840

What is the cost per equivalent unit for materials?

A.$0.56

B.$2.00

C.$1.40

D.$1.5

 

0

 

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more