111. A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:
Budgeted Activity
Activity Cost Pool
Budgeted Cost
Product A
Product B
Activity 1
$87,000
3,000
2,800
Activity 2
$62,000
4,500
5,500
Activity 3
$93,000
2,500
5,250
Annual production and sales level of Product A is 34,300 units, and the annual production and sales level of Product B is 69,550 units. What is the approximate overhead cost per unit of Product B under activity-based costing?A. $3.00B. $2.00C. $10.28D. $15.00E. $2.33
112. A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:
Budgeted Activity
Activity Cost Pool
Budgeted Cost
Product A
Product B
Activity 1
$87,000
3,000
2,800
Activity 2
$62,000
4,500
5,500
Activity 3
$93,000
2,500
5,250
Annual production and sales level of Product A is 34,300 units, and the annual production and sales level of Product B is 69,550 units. What is the approximate overhead cost per unit of Product A under activity-based costing?A. $3.00B. $2.00C. $10.28D. $15.00E. $2.33
113. A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:
Budgeted Activity
Activity Cost Pool
Budgeted Cost
Product A1
Product B2
Activity 1
$48,000
1,200
4,800
Activity 2
$63,000
2,240
4,760
Activity 3
$80,000
7,200
800
Annual production and sales level of Product A1 is 8,480 units, and the annual production and sales level of Product B2 is 22,310 units. What is the approximate overhead cost per unit of Product A1 under activity-based costing?
A. $8.00B. $9.00C. $10.00D. $12.00E. $4.00
114. A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:
Budgeted Activity
Activity Cost Pool
Budgeted Cost
Product A1
Product B2
Activity 1
$48,000
1,200
4,800
Activity 2
$63,000
2,240
4,760
Activity 3
$80,000
7,200
800
Annual production and sales level of Product A1 is 8,480 units, and the annual production and sales level of Product B2 is 22,310 units. What is the approximate overhead cost per unit of Product B2 under activity-based costing?
A. $8.00B. $9.00C. $10.00D. $12.00E. $4.00
Reference: 17_05
Assume that a pet food manufacturer is considering adding two types of pet food to its existing product line. Research had determined that good demand exists for dog food in 40-pound bags and cat food in 1/2pound cans.The company identified the following partial list of activities, costs, and activity drivers expected for the next year:
Activity
Expected Costs
Cost Driver
Handling materials
$105,000
Number of batches made
Storage costs
$820,000
Weight of finished product
Dog Food
Cat Food
Production volume
100,000 units
200,000 units
Batches made
200 batches
150 batches
115. Refer to the data above. What are the overhead rates used to apply material handling (MH) and storage costs (SC) using activity-based costing?
A. MH $300/batch; SC $2.73/unit.
B. MH $300/batch; SC $.20/lb.
C. MH $525/batch; SC $.205/unit.
D. MH $700/batch; SC $.205/lb.
E. MH $700/batch; SC $8.20/lb.
116. Refer to the data in the preceding tables. How much overhead cost will be assigned to each product line using activity-based costing (ABC)?A. Dog food: $462,500; cat food: $462,500.B. Dog food: $860,000; cat food: $65,000.C. Dog food: $60,000; cat food: $45,000.D. Dog food: $800,000; cat food: $20,000.E. Dog food: $320; cat food: $320.
117. Refer to the data above. How much overhead cost will be assigned to each unit of product using activity-based costing (ABC)?A. Dog food: $4.62; cat food: $4.62.B. Dog food: $2.64; cat food: $2.64.C. Dog food: $8.60; cat food: $0.33.D. Dog food: $0.26; cat food: $8.60.E. Dog food: $0.12; cat food: $3.85.
Reference: 17_06
Assume that the Oregon Ice Cream Company is considering the costs of two of their product lines—ice cream sandwiches and dessert bars. The company identified the following partial list of activities, costs, and activity drivers expected for the next year.
Activity
Expected Costs
Cost Driver
Extrusion costs
$637,500
Number batches made
Packaging costs
$44,000
Number of units made
Ice Cream Sandwiches
Dessert Bars
Production volume
350,000 units
200,000 units
Batches made
400 batches
350 batches
118. Refer to the data in the preceding tables. How much overhead cost will be assigned to the ice cream sandwich product line using activity-based costing (ABC)?A. $340,000B. $368,000C. $28,000D. $850.08E. $433,682
119. Refer to the data above. How much overhead cost will be assigned to the dessert bar product line using activity-based costing (ABC)?A. 340,750B. $247,818C. $16,000D. $297,500E. $313,500
120. A company identified the following partial list of activities, costs, and activity drivers expected for the next year:
Activity
Expected Costs
Cost Driver
Extrusion costs
$83,600
Number batches made
Handling costs
$8,800
Number of orders filled
Packaging costs
$40,500
Number of units made
Product A
Product B
Production volume
750,000 units
600,000 units
Batches made
200 batches
750 batches
Orders filled
75
200
Calculate activity rates for each of the three activities using activity-based costing (ABC).A. Extrusion: $304 per batch; handling: $32 per unit; packaging: $.03 per unit.B. Extrusion: $88 per batch; handling: $32 per order; packaging: $.03 per unit. C. Extrusion: $88 per order; handling: $32 per unit; packaging: $.03 per batch.D. Extrusion: $418 per batch; handling: $117.33 per order; packaging: $.054 per unit.E. Extrusion: $118.13 per batch; handling: $44 per order; packaging: $.0675 per unit.
121. A company identified the following partial list of activities, costs, and activity drivers expected for the next year:
Activity
Expected Costs
Cost Driver
Extrusion costs
$83,600
Number batches made
Handling costs
$8,800
Number of orders filled
Packaging costs
$40,500
Number of units made
Product A
Product B
Production volume
750,000 units
600,000 units
Batches made
200 batches
750 batches
Orders filled
75
200
How much overhead in total will be assigned to the Product A line using activity based costing?A. $42,500.
B. $132,900. C. $90,400.D. $66,000.E. $66,450.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more