Question :
111. The debits to Work in Process–Assembly Department for April, together : 1233779
111. The debits to Work in Process–Assembly Department for April, together with data concerning production, are as follows:
April 1, work in process:
Materials cost, 3,000 units
$ 7,500
Conversion costs, 3,000 units,
2/3 completed
6,000
Materials added during April, 10,000 units
26,000
Conversion costs during April
31,000
Goods finished during April, 11,500 units
—
April 30 work in process, 1,500 units,
1/2 completed
—
All direct materials are placed in process at the beginning of the process and the average cost method is used to cost inventories. The materials cost per equivalent unit (to the nearest cent) for April is: A. $2.60B. $2.58C. $3.02D. $2.26
112. The debits to Work in Process–Assembly Department for April, together with data concerning production, are as follows:
April 1, work in process:
Materials cost, 3,000 units
$ 7,500
Conversion costs, 3,000 units,
2/3 completed
6,000
Materials added during April, 10,000 units
26,000
Conversion costs during April
31,000
Goods finished during April, 11,500 units
—
April 30 work in process, 1,500 units,
1/2 completed
—
All direct materials are placed in process at the beginning of the process and the average cost method is used to cost inventories. The conversion cost per equivalent unit (to the nearest cent) for April is: A. $2.70B. $2.53C. $3.02D. $5.60
113. Department E had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $12,500. 14,000 units of direct materials were added during the period at a cost of $28,700. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $32,450 and factory overhead was $18,710. The number of equivalent units of production for the period for conversion if the average cost method is used to cost inventories was: A. 15,650B. 14,850C. 18,000D. 17,250
114. Department E had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $12,500. 14,000 units of direct materials were added during the period at a cost of $28,700. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $32,450 and factory overhead was $18,710. The number of equivalent units of production for the period for materials if the average cost method is used to cost inventories was: A. 15,650B. 18,000C. 17,250D. 17,700
115. Department E had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $12,500. Of the $12,500, $8,000 was for material and $4,500 was for conversion costs. 14,000 units of direct materials were added during the period at a cost of $28,700. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $32,450 and factory overhead was $18,710. If the average cost method is used the material cost per unit (to the nearest cent) would be: A. $2.04B. $1.59C. $1.91D. $2.00
116. Department E had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $12,500. Of the $12,500, $8,000 was for material and $4,500 was for conversion costs. 14,000 units of direct materials were added during the period at a cost of $28,700. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $32,450 and factory overhead was $18,710. Department E had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $12,500. Of the $12,500, $8,000 was for material and $4,500 was for conversion costs. 14,000 units of direct materials were added during the period at a cost of $28,700. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $32,450 and factory overhead was $18,710. If the average cost method is used the conversion cost per unit (to the nearest cent) would be: A. $3.71B. $2.84C. $2.97D. $3.23
117. Which of the following industries would normally use job order costing systems and which would normally use process costing systems?Business consultingChemicalsFoodMovieSoap and cosmeticsWeb designer
Business consultantJob Order
ChemicalsProcess
FoodProcess
Movie studioJob Order
Soap and cosmeticsProcess
Web designerJob order
118. The Desert Springs Water Company has two departments. Purifying and Bottling. The Bottling Department received 62,000 liters from the Purifying Department. During the period, the Bottling Department completed 60,000 liters, including 3,000 liters of work in process at the beginning of the period. The ending work in process was 5,000 liters. How many liters were started and completed during the period?
57,000 liters started and completed (60,000 completed – 3,000 beginning WIP)