Question : 71. If the price paid per unit differs from the standard : 1239595

 

 

71. If the price paid per unit differs from the standard price per unit for direct materials, the variance is termed a: A. variable varianceB. controllable varianceC. price varianceD. volume variance

 

72. The following data is given for the Stringer Company: 

Budgeted production

26,000 units

Actual production

27,500 units

Materials:

 

  Standard price per ounce

$6.50

  Standard ounces per completed unit

8

  Actual ounces purchased and used in production

228,000

  Actual price paid for materials

$1,504,800

Labor:

 

  Standard hourly labor rate

$22 per hour

  Standard hours allowed per completed unit

6.6

  Actual labor hours worked

183,000

  Actual total labor costs

$4,020,000

Overhead:

 

  Actual and budgeted fixed overhead

$1,029,600

  Standard variable overhead rate

$24.50 per standard labor hour

  Actual variable overhead costs

$4,520,000

 

 

  Overhead is applied on standard labor hours. The direct material price variance is: A. 22,800UB. 22,800FC. 52,000UD. 52,000F

 

73. The following data is given for the Stringer Company: 

Budgeted production

26,000 units

Actual production

27,500 units

Materials:

 

  Standard price per ounce

$6.50

  Standard ounces per completed unit

8

  Actual ounces purchased and used in production

228,000

  Actual price paid for materials

$1,504,800

Labor:

 

  Standard hourly labor rate

$22 per hour

  Standard hours allowed per completed unit

6.6

  Actual labor hours worked

183,000

  Actual total labor costs

$4,020,000

Overhead:

 

  Actual and budgeted fixed overhead

$1,029,600

  Standard variable overhead rate

$24.50 per standard labor hour

  Actual variable overhead costs

$4,520,000

 

 

  Overhead is applied on standard labor hours. The direct material quantity variance is: A. 22,800FB. 22,800UC. 52,000FD. 52,000U

 

74. The Lucy Corporation purchased and used 129,000 board feet of lumber in production, at a total cost of $1,548,000. Original production had been budgeted for 22,000 units with a standard material quantity of 5.7 board feet per unit and a standard price of $12 per board foot. Actual production was 23,500 units. Compute the material price variance. A. 0B. 59,400UC. 59,400FD. 6,000U

 

75. The Lucy Corporation purchased and used 129,000 board feet of lumber in production, at a total cost of $1,548,000. Original production had been budgeted for 22,000 units with a standard material quantity of 5.7 board feet per unit and a standard price of $12 per board foot. Actual production was 23,500 units. Compute the material quantity variance. A. 63,000FB. 63,000UC. 59,400FD. 59,400U

 

76. If the wage rate paid per hour differs from the standard wage rate per hour for direct labor, the variance is termed a: A. variable varianceB. rate varianceC. quantity varianceD. volume variance

 

77. If the actual direct labor hours spent producing a commodity differs from the standard hours, the variance is termed a: A. time varianceB. price varianceC. quantity varianceD. rate variance

 

78. The following data relate to direct labor costs for the current period: 

Standard costs

  7,500 hours at $11.40

Actual costs

  6,000 hours at $12.00

 

 

What is the direct labor time variance? A. $  4,500 favorableB. $18,000 unfavorableC. $  3,600 favorableD. $17,100 favorable

 

79. The following data relate to direct labor costs for the current period: 

Standard costs

  6,000 hours at $12.00

Actual costs

  7,500 hours at $11.40

 

 

What is the direct labor rate variance? A. $18,000 unfavorableB. $  4,500 favorableC. $17,100 unfavorableD. $  3,600 favorable

 

80. The following data relate to direct labor costs for the current period: 

Standard costs

9,000 hours at $5.50

Actual costs

8,500 hours at $5.75

 

 

What is the direct labor rate variance? A. $2,250.00 unfavorableB. $2,125.00 unfavorableC. $2,250.00 favorableD. $2,125.00 favorable

 

 

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more