Group 2 unit 9 group assignment

  

Week 9 Group Assignment – Group #6

Schedule Compression and Resource Leveling 

Team members 

Sana Kapur, Shuang Tai, Abdul Shoaib Mohammed, Sreekanth Reddy, and Naga Srinivas Guntupalli

Part 1 Questions (20 points)

1. What is the purpose of a staffing management plan? What does it address?

The main purpose of a staffing management plan is to assign roles and responsibilities and give a clear indication of what is expected from the project team members. It gives an overview of the skill sets required by each team member, and the duration of their role on the project. The staffing management plan will give a snapshot of the staff requirements for the project, the expectations from each team member and the length of time they will be working on the project. 

2. Whom should the project manager consult when performing resource leveling?

The project manager should consider the following team members:

– Sponsors

– Resource manager

– Experts in the particular project field

– Management

– Other project managers

3. Describe the two primary techniques for compressing a schedule?

Schedule compression techniques are applied in cases where the project is not on track with the schedule or behind the allocated timeline. These techniques are applied to primarily compress the schedule without altering or modifying the project scope. If the project scope and deadline are not being modified, it is important to compress the project schedule.

Below are the two key techniques for compressing a schedule:

1. Fast-tracking 

In this technique, those phases or activities that are normally done in a sequence are then performed in parallel for a certain time frame of their project duration. Here, activities on the critical path are performed in parallel instead of series. However, one cannot undertake fast-tracking if the execution of the activities are dependant on the completion of the previous activity. For example, one cannot perform a quality check on a product before its production. If the activities on the critical path depend on each other because of resources, it is still possible to undertake fast-tracking in this instance and speed up the process.

2. Crashing

Crashing can be used to reduce the entire project schedule duration for the lowest additional cost by allocating additional resources. This can be successful as activities are sped up using the extra resources allocated to them. 

4. When crashing a project schedule, describe the two criteria that are considered when considering which activities will be sped up.

The first criteria will be to identify which activities will be along the critical path. Since the critical path is the longest path for the activity and determines how long it will take for each activity to be completed, speeding up activities on the critical path will not result in a change in project schedule.

The second criteria will be evaluation the cost of activities and identifying which activity has the lowest per day cost to speed up. It is not economically beneficial for the project to add further financial resources to speed up activities that cost more (Kloppenborg, 2015). 

Part 3 Resource Leveling (40 points)

Using the data below

  

Activity ID

Activity

Immediate Predecessor

Duration in days

Resource

Work Hours per Day

 

A

Evaluate freezers

2

Alcides

6

 

B

Chart temperatures

6

Joan

4

 

C

Review service record

2

Alcides

 

D

Consult with HVAC engineer

A, B, C

3

Alcides

 

E

Develop construction plan

D

10

Joan

 

F

Complete IC assignment

E

2

Alcides

 

G

Complete ROI analysis

E

5

Joan

 

H

Conduct regulatory review

E

4

Joan

 

I

Obtain construction approval

F, G, H

2

Alcides

a. Create a project schedule in MS Excel ensuring that it reflects the predecessor/successor relationships identified in the table.

b. How long will it take to complete the project?

It will take 26 Days to complete the project.

References:

– Kloppenborg, T.J. (2015).Contemporary Project Management (Third edition). Stamford, CT: Cengage Learning. Pg 222. 

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more